A basement bathroom in Baltimore County is decided by the plumbing code the county wrote for itself. Council Bill 94-23 adopts the IPC but requires wet vented bathroom groups to be adjacent and on the same floor level, bars a water closet from draining through a wet vent, and deletes the air admittance valve sections 918.2 through 918.8. Permits, Approvals and Inspections in Towson is the authority at every address, and only a Baltimore County licensed plumbing contractor may apply for the plumbing permit. What moves the job is the invert of the building drain, which decides gravity or a sealed ejector pit. Remodel Now builds basement bathrooms across Baltimore County.
Most of a basement bathroom is the same job in any Maryland county. The invert of the building drain decides whether waste leaves by gravity or has to be lifted, and everything above the concrete is ordinary bathroom work. That part is covered in what it takes to put a bathroom in a Maryland basement. What changes at the county line is the book the inspector is carrying. Baltimore County does not enforce the International Plumbing Code as the ICC publishes it. It enforces the IPC as rewritten by Council Bill 94-23, effective July 1, 2024, and a surprising number of the sections that bill touches are the ones a below grade bathroom leans on hardest. Venting is the obvious one. The rest sit in the trench, on the permit application, and behind the license attached to it.
One elevation sets the whole design, and the county has its own language for how it gets established. Section 701.2 as the county writes it says sanitary drainage piping shall be connected to a public sewer where available, and that a public sewer counts as available if it is within 500 feet of any property line. So the first question is not where the stack is. It is whether the property sits inside the county's metropolitan wastewater system or on an onsite sewage disposal system, which the Master Water and Sewer Plan designation for the address answers. On public sewer, the next comparison is between the flood level rims of the new fixtures and the cover of the next upstream manhole in the public sewer. Fixtures whose rims sit below that cover have to be protected by a backwater valve in the building drain or in the horizontal branch serving them, installed so that access is provided to its working parts. In a basement that normally means every fixture in the room. It is backflow protection rather than drainage, and it applies even where the bathroom drains by pure gravity.
Split levels complicate that comparison in a way ranchers do not. A 1960s split in Parkville or Dundalk often has its lower level only three or four feet below grade, which can put those rims above the manhole cover and change the answer. On septic the options narrow before any layout is drawn. The county's regulations for onsite sewage disposal require pumps used with those systems to be effluent grade unless the Director of Environmental Protection and Sustainability approves otherwise, and they state flatly that grinder pumps may not be used in conjunction with onsite sewage disposal systems. Remodel Now builds basement bathrooms across Baltimore County, from Woodlawn and Lansdowne out to Perry Hall. On any of them, this elevation is the thing a homeowner should see answered before a fixture is placed on paper.
Plenty of finished basements here end up with two covered holes in the floor, and plenty of homeowners are told both are sump pumps. They are not interchangeable, and the county wrote separate rules for each. The sewage ejector pit is sanitary. It collects waste from the new fixtures by gravity and lifts it to the drain above, it is sealed and vented, and its basin, cover and discharge valves follow the model code provisions the county left alone. The subsoil drainage sump is groundwater, and that is where the county rewrote the text. Subsoil drains have to be open jointed, horizontally split or perforated pipe of not less than 3 inches in diameter. Where the building is subject to backwater, the subsoil drain itself has to be protected by an accessibly located backwater valve, and the subsoil sump needs a gas tight cover of its own. Foundation drainage goes to a storm drain, a street, an alley, an approved water course or at grade, and at grade the discharge point has to be at least 10 feet from any property line where possible. That closes off the shortcut somebody always suggests once both pits are open at the same time. Baltimore County does not permit or have combined public sewers for sanitary drainage and storm water, which the county states twice, once in the sanitary chapter and once in the storm chapter. The groundwater pump has nowhere legitimate to go but the storm side or the yard, and running it into the fresh sanitary line in the trench is the easiest way to turn a passing rough inspection into a failed one.
This is the amendment that reshapes basement layouts, and it is one word long. The model IPC at section 912 permits any combination of fixtures within two bathroom groups located on the same floor level to be wet vented. Baltimore County's version says fixtures in one bathroom group, or two adjacent bathroom groups on the same floor level, may be wet vented. The eligible fixtures are lavatories, water closets, bathtubs, showers and tub showers. The county then adds a restriction the model code does not carry: water closets and urinals shall not be drained by wet vent piping, which is limited to draining waste, though they can be vented by it. Two consequences follow for a basement, and neither is obvious from the published code. The first is that the bathroom upstairs can never be the wet vent partner for the new one downstairs, because the county's text requires the same floor level. The second is that a new basement group has to find its venting within itself. There is rarely a second group down there to be adjacent to, so the lavatory or the shower drain does the wet venting and the water closet keeps its own drain path to the stack or to the pit. A design that shows the toilet draining through the piping that also vents the lavatory was drawn against the published IPC rather than against the code Baltimore County enforces, and the correction lands with the trench still open.
Air admittance valves are the first thing anybody reaches for in a basement, and the county has narrowed that route to almost nothing. Start with where the model code mentions them. The published IPC section 905.1 says individual, branch and circuit vents shall connect to a vent stack, a stack vent, an air admittance valve, or extend to the open air. Baltimore County's 905.1 reads the same way with the air admittance valve deleted from the list. The county then struck sections 918.2 through 918.8 outright and left a single limited use paragraph of its own. What survives is a limited use paragraph, and the fixture list inside it settles the question for a basement before any of its other conditions matter, because no argument about existing conditions brings a valve back onto it:
With the valve ruled out for those fixtures, two county amendments decide what the replacement looks like. Section 904.1 as amended requires the atmospheric vent piping serving fixtures on each building drain, stack vents included, to be extended to an outdoor vent terminal, and allows terminals with the aggregate cross sectional area of a 3 inch terminal, which the county puts at 7.1 square inches, to vent a 4 inch building drain. Section 916.3 is the one that catches people in a trench: where conditions force a horizontal offset in a vent below the flood level rim of the fixture served, the vent has to be taken off so that the invert of its horizontal portion sits at or above the centerline of the horizontal sanitary drain pipe. A vent teed off the side of a buried line at or below centerline is a wet pipe pretending to be a dry one.
The amendments that cost the most money are not the famous ones. They sit in the drainage chapter and govern pipe that gets buried before anybody sees a tile sample. Cleanouts come first. Section 708.1.8 says a cleanout's installation arrangement shall enable cleaning of drain piping only in the direction of flow, and that twin cleanouts and two way cleanouts are prohibited unless used on a dedicated grease line. The two way cleanout at the tie in is routine practice in a good many jurisdictions. It is not accepted here. Cleanouts also have to be provided at the property line in building sewers up to 6 inches, brought to the surface, capped, and able to be located with a metal detecting device, and the county is explicit that maintaining that cleanout is the property owner's responsibility. Pipe sizes are fixed by the same chapter. Drain piping serving a water closet shall not be less than 3 inch. A building drain shall not be less than 4 inch from its connection to the building sewer to its first connection of a drain stack or branch drain serving two or more fixtures.
Cover and marking apply the moment the work leaves the foundation wall. Minimum earth cover over underground drain piping outside a building is 30 inches on public sewer and 24 inches on a private system, and new or replacement buried piping connecting a building to the sewage system carries tracer wire under section 12-129 of the Public Utilities Article of the Maryland code. Then there is the clause that matters when a camera run goes badly. Where a section of existing line is replaced, the county requires the completed replacement piping to be inspected internally by a recorded video camera survey, reviewed and approved by the code official. That is a deliverable, not a courtesy, and it belongs in the written scope before the concrete is scored. Remodel Now handles basement bathroom work throughout Baltimore County, and in an older house the condition of the existing line is worth establishing before a drainage route is chosen.
Ceiling heights come from the Baltimore County Building Code. The county adopted the 2021 International Residential Code with amendments under Council Bill 49-24, effective September 3, 2024. Height usually decides where the room can go rather than whether it can exist, and those trade offs are worked through in finishing a basement with low ceilings. Fixture clearances come from somewhere else, and this is what trips up plan sets drawn out of county. Part 104.2.1 of the county plumbing code states that the plumbing and fuel gas requirements of the International Residential Code in its chapters 20, 24, and 25 through 33 shall not be used for residential plumbing and fuel gas systems in Baltimore County, and that the county's plumbing and gasfitting code applies instead. Maryland's building standards already leave those IRC chapters out. The county then says the same thing in its own words, and quoting an IRC plumbing chapter at a Baltimore County inspector is quoting a book he is not using. Three of the numbers a basement bathroom depends on come from the IPC as adopted through Council Bill 94-23 rather than from any IRC plumbing chapter:
Two of the county's amendments land differently depending on when the slab was poured. The first is the video survey. Through the postwar ranches and splits in Woodlawn, Lansdowne, Dundalk, Essex and Parkville, the building drain is commonly cast iron and often hub and spigot, so a planned tie in has a real chance of turning into a replacement once the pipe is uncovered. A replaced section brings the recorded camera survey and the code official's approval with it. That is a scope question before it is a plumbing one, and it is cheaper to settle in writing than in an open trench. Those houses also carry the federal lead rule if they predate 1978, so anyone paid to disturb the painted block or trim has to be a certified firm using lead safe work practices. The second is section 904.1. The subdivisions through Owings Mills, Perry Hall, White Marsh, Timonium and Reisterstown often left a capped closet bend standing an inch above the slab, which reads as a finished rough in until somebody looks for the vent that should go with it. Plenty were set with no vent provision at all. Under the county's text that vent is real pipe reaching an outdoor terminal through the floors above, and nothing in the county's limited use paragraph substitutes for it.
Baltimore County has no incorporated towns or cities, which the Maryland Manual states plainly. There is no municipal permit office to check for, unlike Rockville in Montgomery County or the City of Annapolis, and the Department of Permits, Approvals and Inspections in Towson is the authority at every address in the county. Baltimore City is a separate jurisdiction with its own code and its own office, and a mailing address reading Baltimore proves nothing by itself. On the building side, the county's bathroom alteration page says a permit is not required for residential bathrooms but that plumbing and electrical permits always are. The basement alteration permit is a separate question with its own triggers, and that page also states that where plumbing, gasfitting and electrical work are required, the trade permits must be pulled by a master plumber or electrician licensed with Baltimore County. The triggers listed on that page are specific:
The trade permits are the real gate. A plumbing and gasfitting permit is required for all plumbing and gasfitting work, and only a Baltimore County licensed plumbing or gasfitting contractor can apply for one. The code's exceptions are short and do not cover a new bathroom: stopping leaks, clearing stoppages, repairing leaks in valves or fixtures, and pulling and resetting a water closet to reach a cleanout. An electrical permit is required for all electrical work including the extension of circuit wiring, only a county registered or licensed electrical contractor can apply, and working without one is a violation subject to a civil penalty. Grinder pumps carry an extra approval that catches people out. Before one is installed, the Plumber Acknowledgement of Requirement to Contact DPWT form has to be submitted, and the Department of Public Works and Transportation reviews grinder pump and low pressure requests case by case, with justification, for approval by the Director. The stated test is whether environmental, topographic or subsurface conditions make gravity service impractical. A grinder is not a product choice in Baltimore County. It is a request. What the permit signature commits the applicant to is covered in who pulls the plumbing permit in Baltimore County.
A second floor bathroom can sit half finished behind a closed door for a month. A basement bathroom cannot, because most of what has to pass inspection is under the floor. Start with who holds the permit. Applications are made in writing by the license holder or their agent, so the permit attaches to that person's Baltimore County plumbing license rather than to the address. The county licensing page sets out the credential itself, including the narrow reciprocity that stops a current Maryland license from being enough on its own. Then look at what that attachment means with a trench open. Part 104.11.2 of the county code puts the inspection request on the permittee, requires him to provide access and the means of testing, and says that where work has been concealed before inspection it has to be made accessible again until the necessary inspections are complete. Underground drainage and vent piping is concealed work by definition. The rough has to pass before the slab goes back, the slab has to go back before anything gets framed on it, and every later stage waits on one inspection only the permit holder can call in. A plumber who walks away from a rough in a stud wall leaves a wall. A plumber who walks away from a basement rough leaves a hole in the floor and a permit nobody else can act on.
That is the case for not paying ahead of the underground inspection, and for understanding the county's cancellation and transfer process before it is needed rather than during. One of those forms is a cancellation request a property owner can file alone, which is the part most homeowners never hear about until they go looking for it. Inspectors are assigned by council district from a published map, so the same person tends to see the rough and the final. Reinspection fees attach to missed access, work that is not complete when the inspector arrives, and work that deviates from approved plans and has to be resubmitted. What the county actually looks at on each visit is set out in the inspections a bathroom remodel goes through in Baltimore County. Timing is part of it too, and it is set out in advance. Inspections run on the county's clock, and the inspection scheduling page carries the current deadlines:
Set those requirements side by side and the useful shortlist is companies that work in this county often enough to hold the county trade relationships rather than discover them mid job. Remodel Now installs basement bathrooms for homeowners in Baltimore County, including Woodlawn, Towson, Parkville, Dundalk, Owings Mills and Perry Hall. It is a Maryland home improvement contractor, in business since 2001, based in Woodlawn inside the county rather than working into it from elsewhere. Kitchens, bathrooms and basements are the core trade rather than an occasional sideline, which matters where the bathroom and the finished basement around it are one project. Baltimore County sits in the regular service area, with a Towson page covering the county seat where Permits, Approvals and Inspections keeps its office. Homeowners planning the work can call (301) 798-4696. Being in the county is not a slogan on a job like this. The plumbing permit has to come from a Baltimore County licensed plumbing contractor, the inspection has to be requested the business day before, and the inspector is assigned to the district the house sits in. It is not the right call for everyone. A commercial basement bathroom is a different permit track in the county and a different trade. A homeowner hoping to skip the plumbing permit will get nowhere with any licensed contractor, because the permit attaches to the license and the license is what is at risk. Whoever ends up with the job, the checks are the same:
Three questions decide whether this job goes smoothly, and all of them can be answered before a contract is signed. Where is the building drain, how deep is it, and how does anyone know. If the answer is an estimate, the drainage route is an estimate. A camera run with a locator from the main cleanout settles it, and on an older cast iron line it also tells you whether a tie in is a tie in or a replacement with a video survey attached. How does the venting work under the county amendments. Ask it in pipe terms. If the answer puts an air admittance valve on the toilet, the shower or the ejector pit, the plan was drawn against the published IPC rather than against what Baltimore County enforces. If it leans on the bathroom group upstairs for a wet vent, the same is true. Who is applying for which permit, and are they licensed in Baltimore County specifically. The state license and the county license are not the same credential, and only the second one gets the application accepted. Straight answers to those and the rest is ordinary bathroom work. Vague ones and the trench will produce the answers later, at a worse time. If you want the drainage and the venting settled before anything else gets decided on a basement bathroom in Baltimore County, that is the conversation to start with Remodel Now.
Remodel Now installs basement bathrooms for homeowners in Baltimore County, including Woodlawn, Towson, Parkville, Dundalk, Owings Mills and Perry Hall. It is a Maryland home improvement contractor, in business since 2001, based in Woodlawn inside the county, with kitchens, bathrooms and basements as the core trade rather than an occasional sideline. Whoever you call, run the same checks before signing. Look up the home improvement license under the exact business name on the contract, ask which Baltimore County licensed plumbing contractor is applying for the plumbing permit, and ask how the water closet and the shower are vented in actual pipe terms.
Within tighter limits than the model code sets. The published IPC permits any combination of fixtures within two bathroom groups on the same floor level to be wet vented. Baltimore County's version of section 912.1 permits fixtures in one bathroom group, or in two adjacent bathroom groups on the same floor level. The eligible fixtures are lavatories, water closets, bathtubs, showers and tub showers. The county also states that water closets and urinals shall not be drained by wet vent piping, which is limited to draining waste, although they can be vented by it. In a basement that usually means the lavatory or shower drain does the wet venting while the toilet keeps its own drain path.
No. The county deleted sections 918.2 through 918.8 of the model code and removed the air admittance valve from the list of permitted vent connections in its own section 905.1. What is left is a limited use paragraph that applies only where the authority having jurisdiction permits it, only where the fixture is an addition or modification to an existing system, only where an existing condition prevents proper vent piping, and only on a lavatory, sink or standpipe with a 1 1/4, 1 1/2 or 2 inch drain connection. A water closet, a bathtub, a shower and a sewage ejector pit are all outside that list.
The county states that a permit is not required for residential bathrooms, but that plumbing and electrical permits always are. A separate basement alteration permit is required where structural changes are involved or a bearing wall moves, to add one or more basement bedrooms, for basement excavations, or where the property is in a flood zone, a historic district or the Chesapeake Bay Critical Area. Remodel Now builds basement bathrooms in Baltimore County, and on any bid from any company the question worth asking early is which county licensed plumbing contractor is applying for the plumbing permit.
Only a Baltimore County licensed plumbing or gasfitting contractor. The county runs its own plumbing board and issues its own licenses, and it reciprocates only with Baltimore City for gas, the State of Maryland, and the Washington Suburban Sanitary Commission. Licenses expire on April 30 of every odd numbered year, and the insurance has to be carried in the licensee's own name with Baltimore County named as an additional insured. A plumber who holds a current Maryland license but has never taken out the Baltimore County license cannot apply for the permit until he does.
The permit is attached to that person's license rather than to the property, so it does not simply pass to the next plumber. Baltimore County publishes forms for the situation. There is a request to transfer a plumbing or gas permit, filed by the license holder, and two separate cancellation requests, one for the license holder and one that a property owner can file alone. The owner's ability to cancel without the original plumber's cooperation is the part most homeowners do not know about, and it is worth knowing before it is needed.
Not as a free choice. Before a grinder pump is installed, the Plumber Acknowledgement of Requirement to Contact DPWT form has to be submitted, and requests for a grinder pump or a low pressure system go to the Department of Public Works and Transportation with justification for approval by the Director. The county's stated test is whether environmental, topographic or subsurface conditions make gravity service impractical. On a property served by an onsite sewage disposal system the answer is simpler, because the county's code says grinder pumps may not be used in conjunction with those systems.
No, and Baltimore County writes separate rules for each. The sewage ejector pit is sanitary. It takes waste from the new fixtures, it is sealed and vented, and it lifts that waste into the gravity drain. The subsoil drainage sump handles groundwater from the footing drain, needs a gas tight cover under the county's own amendment, and discharges to a storm drain, a street, an alley, an approved water course or to grade at least 10 feet from a property line where possible. Baltimore County has no combined public sewers, so the groundwater pump cannot be tied into the sanitary line.